Granite Westchase II

Granite Westchase II

About This Project

General Contractor – Hoar Construction, LLC

Architect – Kirksey Architecture

Structural Engineer – Haynes Whaley Associates

Contraqct Value - $9,053,195

Granite Westchase II consisted of one 15 story 350,000 square foot office tower, an 8 story 345,000 square foot precast garage and 54,000 square feet of site concrete.  The office tower was a pan slab structure with an odd geometry that was completed one month ahead of schedule.

Materials Used

Foundations- spread footings.

Elevated Slabs- Post tension pan slabs.

Vertical Support- 28x48 interior columns with 30x30 columns at the exterior.

Project Timeline

6 Months

Division:

Project Photos